The heating system is the heart of every home, so it’s important to take care of it right from the initial planning stage of construction.

Once the contract with AmeriGas is signed, our technical department will handle all the paperwork and work involved in installing the LPG tank and filling it for the first time. See what the entire process looks like, step by step.

signing contract
technical requirements

Formalities

  • The designer visits the construction site and, based on a site inspection and the design map, prepares a construction plan that indicates the location of the tank and its connection to the building
  • Completion of official formalities related to the planned installation of the tank and gas system at the architecture or urban planning department (of the county, municipal, or district office)
  • Once the necessary permits have been obtained, construction of the system may begin

System construction and installation

  • Preparation of the excavation for the system
  • Submission of a tank acceptance report to the Office of Technical Inspection prior to backfilling (applies to underground tanks)
  • Delivery and installation of the tank (including: installation of the system, tank grounding, pressure-reducing sets, gas meter box, pressure leak test of the system; measurement of tank grounding, and others)
  • Acceptance of the tank prior to backfilling by the Technical Inspection Inspector (applies to underground tanks)
  • Backfilling of excavations (applies to underground tanks)
  • Preparation of the excavation for installation
  • Notification of tank acceptance prior to backfilling to the Office of Technical Inspection (applies to underground tanks)
  • Delivery and installation of the tank (including: installation of the system, tank grounding, reducer sets, gas box, pressure leak test of the system; measurement of tank grounding, and others)
  • Acceptance of the tank prior to backfilling by the Technical Supervision Inspector (applies to underground tanks)
  • Backfilling of excavations (applies to underground tanks)
installing heating
car filling lpg

Filling the tank

  • Filling the tank
  • Reporting the filled tank to the Technical Inspection Authority
  • Reporting the completion of construction to the Building Authority (if required)

How can we help?

Any questions? Fill in the form or give us a call.

To be able to send the message, fill in the required fields.
Your message has been sent. We will contact you soon.
Full name
Telephone number
E-mail address
Postal code (XX-XXX)
Tell us how we can help
Full Close

Choose a subject: